Skip to content

Plannings and objectives

The objective plannings are the monitoring calendar that allows managing the objectives defined for a specific period. This page describes the complete workflow: creating the planning, the objectives, their measures, deviations, and monitoring.

  1. Go to Management Systems → Objective Plannings and click New.
  2. Fill in at least the mandatory data marked with an asterisk.
  3. Include the objectives planned for this scheduling from the Objectives tab.
  1. From Management Systems → Objective Plannings, enter a planning.
  2. In the Objectives tab, click New.
  3. Fill in the general data of the objective (fields with an asterisk are mandatory).
  4. Expand the information in the available tabs:
    • Measures: create and link preventive measures to the objective.
    • Monitoring: view the planning and responsibility of the objective.
    • Attachments: add documents to expand the information.
    • Employees with special permission: link employees with read or write permission. It is recommended to indicate the reason for access.

How to create a measure associated with an objective

Section titled “How to create a measure associated with an objective”

Measures associated with an objective have a particularity: they allow recording deviations and creating corrective measures on those deviations.

  1. From the objective detail screen, go to the Measures tab and click New.
  2. Fill in the general data (fields with an asterisk mandatory; at least one scope).
  3. Expand the information in the corresponding tabs.

How to record a deviation and its corrective measure

Section titled “How to record a deviation and its corrective measure”
  1. From the measure detail screen, enter the Deviations tab and click New.
  2. Fill in the general data (fields with an asterisk mandatory).
  3. Enter the Deviation Measures tab and click New to record the corrective measure.
  1. Access the Monitoring tab of the objective.
  2. Fill in the fields as needed.

How to generate a report of an objective planning

Section titled “How to generate a report of an objective planning”
  1. Go to Management Systems → Objective Plannings and select the planning whose report you want to generate.
  2. Click the Generate report button.
  3. Choose the Objective Planning template.
  4. Click Accept.

Source: M-SO-19-04-02 «Management Systems User Manual», version v.2, 08/04/2020.